Church 69 kV

PJM queue ID AF2-109 Terminal status

Queue IDAF2-109
Project nameChurch 69 kV
Status (as published)Withdrawn
SubstationChurch
Point of interconnectionChurch 69 kV
CountyQueen Anne's
StateMD
Voltage69 kV
Capacity10 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2022-10-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity10
Mfo20
Withdrawn Date8/21/2020