Substation Scout

Greenville-West Milton 138 kV

PJM queue ID AF2-079 Terminal status

Queue IDAF2-079
Project nameGreenville-West Milton 138 kV
Status (as published)Withdrawn
SubstationGreenville-West Milton
Point of interconnectionGreenville-West Milton 138 kV
CountyDarke
StateOH
Voltage138 kV
Capacity99 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-10-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy165
Mw Capacity99
Mfo165
Withdrawn Date9/19/2023

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.