Nucor Steel-Suffolk 230 kV

PJM queue ID AF2-073 Terminal status

Queue IDAF2-073
Project nameNucor Steel-Suffolk 230 kV
Status (as published)Withdrawn
SubstationNucor Steel-Suffolk
Point of interconnectionNucor Steel-Suffolk 230 kV
CountyGates
StateNC
Voltage230 kV
Capacity54.9 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2024-03-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy90
Mw Capacity54.9
Mfo90
Withdrawn Date7/2/2020