Plaintation Creek 69 kV

PJM queue ID AF2-055 Terminal status

Queue IDAF2-055
Project namePlaintation Creek 69 kV
Status (as published)Withdrawn
SubstationPlaintation Creek
Point of interconnectionPlaintation Creek 69 kV
CountyNorthampton
StateVA
Voltage69 kV
Capacity27 MW
Resource (as published)Storage; Solar
Resource categoryHybrid (normalised for filtering)
Target commercial operation2025-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy45
Mw Capacity27
Mfo45
Withdrawn Date6/4/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.