Ladysmith CT-St. Johns 230 kV

PJM queue ID AF2-049 Terminal status

Queue IDAF2-049
Project nameLadysmith CT-St. Johns 230 kV
Status (as published)Withdrawn
SubstationLadysmith CT-St. Johns
Point of interconnectionLadysmith CT-St. Johns 230 kV
CountyCaroline
StateVA
Voltage230 kV
Capacity34.5 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2021-12-01
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy60
Mw Capacity34.5
Mfo180
Withdrawn Date9/12/2023

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.