Substation Scout

Carll's Corner Battery Storage

PJM queue ID AF2-020 Terminal status

Queue IDAF2-020
Project nameCarll's Corner Battery Storage
Status (as published)Withdrawn
SubstationCarll's Corner
Point of interconnectionCarll's Corner 69 kV
CountyCumberland
StateNJ
Voltage69 kV
Capacity8 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2029-05-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity8
Mfo20
Withdrawn Date5/7/2025

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.