Substation Scout

Denville Storage Facility

PJM queue ID AF1-324 Terminal status

Queue IDAF1-324
Project nameDenville Storage Facility
Status (as published)Withdrawn
SubstationGreystone-West Denville
Point of interconnectionGreystone-West Denville 34.5 kV
CountyMorris
StateNJ
Voltage34.5 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2021-10-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity0
Mfo20
Withdrawn Date12/3/2020

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.