Substation Scout

Vernon 115 kV

PJM queue ID AF1-303 Terminal status

Queue IDAF1-303
Project nameVernon 115 kV
Status (as published)Withdrawn
SubstationVernon
Point of interconnectionVernon 115 kV
CountyAtlantic
StateNJ
Voltage115 kV
Capacity21.4 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2022-05-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy107
Mw Capacity21.4
Mfo107
Withdrawn Date2/18/2020

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.