Louisa-South Anna 230 kV

PJM queue ID AF1-301 Terminal status

Queue IDAF1-301
Project nameLouisa-South Anna 230 kV
Status (as published)Withdrawn
SubstationLouisa-South Anna
Point of interconnectionLouisa-South Anna 230 kV
CountyLouisa
StateVA
Voltage230 kV
Capacity70 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2022-12-31
Source datasetcycle

Additional filed fields

DeveloperInvenergy Solar Project Development LLC
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleTC1
StagePHASE 1
Mw Energy117.0
Mw Capacity70.0
Mfo117.0
Submitted Date9/30/2019
Withdrawn Date6/24/2024
Withdrawn RemarksCustomer Milestone Not Met
Last Updated6/27/2024