Substation Scout

Desoto 345 kV

PJM queue ID AF1-298 Terminal status

Queue IDAF1-298
Project nameDesoto 345 kV
Status (as published)Withdrawn
SubstationDesoto
Point of interconnectionDesoto 345 kV
CountyDelaware
StateIN
Voltage345 kV
Capacity84 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2023-10-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy200
Mw Capacity84
Mfo200
Withdrawn Date3/6/2020

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.