Substation Scout

Lewis Run-Pierce Brook 3 230 kV

PJM queue ID AF1-278 Terminal status

Queue IDAF1-278
Project nameLewis Run-Pierce Brook 3 230 kV
Status (as published)Withdrawn
SubstationLewis Run-Pierce Brook 3
Point of interconnectionLewis Run-Pierce Brook 3 230 kV
CountyMc Kean
StatePA
Voltage230 kV
Capacity53.4 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2024-06-29
Source datasetcycle

Additional filed fields

DeveloperMcKean Solar, LLC
Transmission OwnerPENELEC
Project TypeGeneration Interconnection
CycleTC1
StagePHASE 1
Mw Energy80.0
Mw Capacity53.44
Mfo280.0
Submitted Date9/30/2019
Withdrawn Date6/21/2024
Withdrawn RemarksCustomer Milestone Not Met
Last Updated6/24/2024

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.