PJM queue ID AF1-277 Terminal status

Queue IDAF1-277
Project nameLewis Run-Pierce Brook 2 230 kV
Status (as published)Withdrawn
SubstationLewis Run-Pierce Brook 2
Point of interconnectionLewis Run-Pierce Brook 2 230 kV
CountyMcKean
StatePA
Voltage230 kV
Capacity67 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2024-06-29
Source datasetcycle

Additional filed fields

DeveloperMcKean Solar, LLC
Transmission OwnerPENELEC
Project TypeGeneration Interconnection
CycleTC1
StagePHASE 1
Mw Energy100.0
Mw Capacity67.0
Mfo200.0
Submitted Date9/30/2019
Withdrawn Date6/21/2024
Withdrawn RemarksCustomer Milestone Not Met