Substation Scout

Avon-North Clark 345 kV

PJM queue ID AF1-251 Terminal status

Queue IDAF1-251
Project nameAvon-North Clark 345 kV
Status (as published)Withdrawn
SubstationAvon-North Clark
Point of interconnectionAvon-North Clark 345 kV
CountyClark
StateKY
Voltage345 kV
Capacity132 MW
Resource (as published)Solar; Storage
Resource categoryHybrid (normalised for filtering)
Target commercial operation2023-05-15
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy220
Mw Capacity132
Mfo220
Withdrawn Date9/13/2023

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.