Tasley 25 kV

PJM queue ID AF1-243 Terminal status

Queue IDAF1-243
Project nameTasley 25 kV
Status (as published)Withdrawn
SubstationTasley
Point of interconnectionTasley 25 kV
CountyAccomack
StateVA
Voltage25 kV
Capacity5 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2020-06-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy5
Mw Capacity5
Mfo5
Withdrawn Date10/9/2020

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.