Substation Scout

Nittany-Zion 46 kV

PJM queue ID AF1-214 Terminal status

Queue IDAF1-214
Project nameNittany-Zion 46 kV
Status (as published)Withdrawn
SubstationNittany-Zion
Point of interconnectionNittany-Zion 46 kV
CountyCentre
StatePA
Voltage46 kV
Capacity12 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2022-05-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity12
Mfo20
Withdrawn Date12/3/2020

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.