Plano 345 kV

PJM queue ID AF1-200 Terminal status

Queue IDAF1-200
Project namePlano 345 kV
Status (as published)Withdrawn
SubstationPlano
Point of interconnectionPlano 345 kV
CountyKendall
StateIL
Voltage345 kV
Capacity2,035 MW
Resource (as published)Not Specified
Resource categoryNot reported (normalised for filtering)
Target commercial operation2025-01-31
Source datasetcycle

Additional filed fields

DeveloperSOO Green HVDC Link ProjectCo, LLC
Transmission OwnerComEd
Project TypeMerchant Transmission
CycleTC1
StagePHASE 2
Mw Energy2100.0
Mw Capacity2035.0
Mfo2100.0
Submitted Date9/25/2019
Withdrawn Date1/22/2025
Withdrawn RemarksCustomer Initiated Withdrawal
Last Updated1/27/2025