Moshannon-Milesburg 230 kV IV
PJM queue ID AF1-142 Terminal status
| Queue ID | AF1-142 |
|---|---|
| Project name | Moshannon-Milesburg 230 kV IV |
| Status (as published) | Withdrawn |
| Substation | Moshannon-Milesburg IV |
| Point of interconnection | Moshannon-Milesburg 230 kV IV |
| County | Clearfield |
| State | PA |
| Voltage | 230 kV |
| Capacity | 121.4 MW |
| Resource (as published) | Solar,Storage,Hybrid |
| Resource category | Hybrid (normalised for filtering) |
| Target commercial operation | 2022-04-01 |
| Source dataset | cycle |
Additional filed fields
| Developer | Moonlight Flats Solar Power, LLC |
|---|---|
| Transmission Owner | APS |
| Project Type | Generation Interconnection |
| Cycle | TC1 |
| Stage | PHASE 1 |
| Mw Energy | 202.4 |
| Mw Capacity | 121.44 |
| Mfo | 328.9 |
| Submitted Date | 9/4/2019 |
| Withdrawn Date | 1/22/2025 |
| Withdrawn Remarks | Customer Milestone Not Met |
| Last Updated | 1/27/2025 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.