Gristmill 345 kV

PJM queue ID AF1-113 Terminal status

Queue IDAF1-113
Project nameGristmill 345 kV
Status (as published)Withdrawn
SubstationGristmill
Point of interconnectionGristmill 345 kV
CountyAuglaize
StateOH
Voltage345 kV
Capacity137.3 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2022-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy180
Mw Capacity137.3
Mfo180
Withdrawn Date9/14/2023