Oyster Creek 230 kV III
PJM queue ID AF1-101 Terminal status
| Queue ID | AF1-101 |
|---|---|
| Project name | Oyster Creek 230 kV III |
| Status (as published) | Withdrawn |
| Substation | Oyster Creek III |
| Point of interconnection | Oyster Creek 230 kV III |
| County | Ocean |
| State | NJ |
| Voltage | 230 kV |
| Capacity | 224.8 MW |
| Resource (as published) | Wind |
| Resource category | Wind (normalised for filtering) |
| Target commercial operation | 2022-11-23 |
| Source dataset | serial |
Additional filed fields
| Project Type | Generation Interconnection |
|---|---|
| Mw Energy | 800 |
| Mw Capacity | 224.8 |
| Mfo | 800 |
| Withdrawn Date | 7/15/2021 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.