PJM queue ID AF1-099 Terminal status
| Queue ID | AF1-099 |
|---|---|
| Project name | Moshannon-Milesburg 230 kV III |
| Status (as published) | Withdrawn |
| Substation | Moshannon-Milesburg III |
| Point of interconnection | Moshannon-Milesburg 230 kV III |
| County | Clearfield |
| State | PA |
| Voltage | 230 kV |
| Capacity | 75.9 MW |
| Resource (as published) | Solar,Storage,Hybrid |
| Resource category | Hybrid (normalised for filtering) |
| Target commercial operation | 2022-04-01 |
| Source dataset | cycle |
Additional filed fields
| Developer | Moonlight Flats Solar Power, LLC |
|---|---|
| Transmission Owner | APS |
| Project Type | Generation Interconnection |
| Cycle | TC1 |
| Stage | PHASE 1 |
| Mw Energy | 126.5 |
| Mw Capacity | 75.9 |
| Mfo | 126.5 |
| Submitted Date | 9/4/2019 |
| Withdrawn Date | 1/22/2025 |
| Withdrawn Remarks | Customer Milestone Not Met |
| Last Updated | 1/27/2025 |