Substation Scout

New Road 230 kV

PJM queue ID AF1-066 Terminal status

Queue IDAF1-066
Project nameNew Road 230 kV
Status (as published)Withdrawn
SubstationNew Road
Point of interconnectionNew Road 230 kV
CountyLoudoun
StateVA
Voltage230 kV
Capacity50 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2021-11-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy50
Mw Capacity50
Mfo170
Withdrawn Date8/8/2023