Substation Scout

Brodnax-South Hill 115 kV

PJM queue ID AF1-059 Terminal status

Queue IDAF1-059
Project nameBrodnax-South Hill 115 kV
Status (as published)Withdrawn
SubstationBrodnax-South Hill
Point of interconnectionBrodnax-South Hill 115 kV
CountyMecklenburg
StateVA
Voltage115 kV
Capacity99.2 MW
Resource (as published)Solar; Storage
Resource categoryHybrid (normalised for filtering)
Target commercial operation2021-10-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy99.2
Mw Capacity99.2
Mfo99.2
Withdrawn Date9/12/2023

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.