Substation Scout

Clinton-Stuart 345 kV

PJM queue ID AF1-035 Terminal status

Queue IDAF1-035
Project nameClinton-Stuart 345 kV
Status (as published)Withdrawn
SubstationClinton-Stuart
Point of interconnectionClinton-Stuart 345 kV
CountyHighland
StateOH
Voltage345 kV
Capacity60 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2021-11-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy100
Mw Capacity60
Mfo100
Withdrawn Date6/12/2019

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.