Substation Scout

Cedar Creek-Silver Run 230 kV

PJM queue ID AF1-025 Terminal status

Queue IDAF1-025
Project nameCedar Creek-Silver Run 230 kV
Status (as published)Withdrawn
SubstationCedar Creek-Silver Run
Point of interconnectionCedar Creek-Silver Run 230 kV
CountyNot reported
StateNot reported
Voltage230 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Not reported
Resource categoryNot reported (normalised for filtering)
Target commercial operation2019-05-03
Source datasetserial

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project TypeUpgrade Request
Withdrawn Date9/21/2020

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.