Substation Scout

Charles County Solar I

PJM queue ID AF1-005

Queue IDAF1-005
Project nameCharles County Solar I
Status (as published)Suspended
SubstationGrayton-Ripley
Point of interconnectionGrayton-Ripley 69 kV
CountyCharles
StateMD
Voltage69 kV
Capacity9.9 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2028-09-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity9.9
Mfo20