Substation Scout

Charles County Solar II

PJM queue ID AF1-003 Terminal status

Queue IDAF1-003
Project nameCharles County Solar II
Status (as published)Withdrawn
SubstationHawkins Gate-Billingsley Rd
Point of interconnectionHawkins Gate-Billingsley Rd 69 kV
CountyCharles
StateMD
Voltage69 kV
Capacity9.5 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2027-09-30
Source datasetserial

Tracked changes

2 changes observed between weekly snapshots of the PJM queue since PJM tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-09-21 Status change n/a Pending Termination → Withdrawn
2026-09-07 Terminal status 9.5 Suspended → Pending Termination

Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity9.5
Mfo20

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.