Galion-Roberts South II 138 kV

PJM queue ID AE2-324 Terminal status

Queue IDAE2-324
Project nameGalion-Roberts South II 138 kV
Status (as published)Withdrawn
SubstationGalion-Roberts South II
Point of interconnectionGalion-Roberts South II 138 kV
CountyMarion
StateOH
Voltage138 kV
Capacity20.3 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2022-12-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20.3
Mw Capacity20.3
Mfo120.3
Withdrawn Date6/24/2022

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.