Wilmington-Davis Creek

PJM queue ID AE2-310 Terminal status

Queue IDAE2-310
Project nameWilmington-Davis Creek
Status (as published)Withdrawn
SubstationWilmington-Davis Creek
Point of interconnectionWilmington-Davis Creek
CountyKankakee
StateIL
VoltageNot reported
Capacity67 MW
Resource (as published)Solar; Storage
Resource categoryHybrid (normalised for filtering)
Target commercial operation2021-05-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy85
Mw Capacity67
Mfo85
Withdrawn Date2/7/2020

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.