Substation Scout

Dauphin-Pine Grove 69kV

PJM queue ID AE2-293 Terminal status

Queue IDAE2-293
Project nameDauphin-Pine Grove 69kV
Status (as published)Withdrawn
SubstationDauphin-Pine Grove
Point of interconnectionDauphin-Pine Grove 69kV
CountyDauphin
StatePA
Voltage69 kV
Capacity20 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2020-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity20
Mfo20
Withdrawn Date4/4/2019

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.