PJM queue ID AE2-277 Terminal status

Queue IDAE2-277
Project nameMcDowell 138 kV
Status (as published)Withdrawn
SubstationMcDowell
Point of interconnectionMcDowell 138 kV
CountyMercer
StatePA
Voltage138 kV
Capacity16 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operationNot reported
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy38.2
Mw Capacity16
Mfo38.2
Withdrawn Date3/30/2022