Altoona-Raystown 230 kV

PJM queue ID AE2-264 Terminal status

Queue IDAE2-264
Project nameAltoona-Raystown 230 kV
Status (as published)Withdrawn
SubstationAltoona-Raystown
Point of interconnectionAltoona-Raystown 230 kV
CountyBlair
StatePA
Voltage230 kV
Capacity48 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2022-06-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy80
Mw Capacity48
Mfo80
Withdrawn Date6/6/2023

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.