Substation Scout

Purdy Sw.-Reams 115 kV

PJM queue ID AE2-250 Terminal status

Queue IDAE2-250
Project namePurdy Sw.-Reams 115 kV
Status (as published)Withdrawn
SubstationPurdy Sw.-Reams
Point of interconnectionPurdy Sw.-Reams 115 kV
CountyGreensville
StateVA
Voltage115 kV
Capacity54 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2021-09-30
Source datasetcycle

Additional filed fields

DeveloperWyatt Mill Solar, LLC
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleTC1
StagePHASE 2
Mw Energy82.5
Mw Capacity54.0
Mfo82.5
Submitted Date3/26/2019
Withdrawn Date1/22/2025
Withdrawn RemarksCustomer Milestone Not Met
Last Updated1/27/2025