Substation Scout

Reybold 12 kV

PJM queue ID AE2-238 Terminal status

Queue IDAE2-238
Project nameReybold 12 kV
Status (as published)Withdrawn
SubstationReybold
Point of interconnectionReybold 12 kV
CountyNew Castle
StateDE
Voltage12 kV
Capacity3.4 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2021-05-14
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy8
Mw Capacity3.36
Mfo8
Withdrawn Date9/17/2019

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.