Substation Scout

Hosier Road Solar II

PJM queue ID AE2-229 Terminal status

Queue IDAE2-229
Project nameHosier Road Solar II
Status (as published)Withdrawn
SubstationSuffolk
Point of interconnectionSuffolk 34 kV
CountyCity of Suffolk
StateVA
Voltage34 kV
Capacity9 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2022-11-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy15
Mw Capacity9
Mfo15
Withdrawn Date4/23/2021