Substation Scout

Eldean Solar

PJM queue ID AE2-218 Terminal status

Queue IDAE2-218
Project nameEldean Solar
Status (as published)Withdrawn
SubstationEldean
Point of interconnectionEldean 138 kV
CountyMiami
StateOH
Voltage138 kV
Capacity106 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2024-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy178
Mw Capacity106
Mfo178
Withdrawn Date6/3/2025

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.