Substation Scout

Gaston-Desoto 138 kV

PJM queue ID AE2-170 Terminal status

Queue IDAE2-170
Project nameGaston-Desoto 138 kV
Status (as published)Withdrawn
SubstationGaston-Desoto
Point of interconnectionGaston-Desoto 138 kV
CountyDelaware
StateIN
Voltage138 kV
Capacity50 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2022-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy50
Mw Capacity50
Mfo250
Withdrawn Date1/30/2020

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.