Belmont-Harrison 500 kV II
PJM queue ID AE2-168 Terminal status
| Queue ID | AE2-168 |
|---|---|
| Project name | Belmont-Harrison 500 kV II |
| Status (as published) | Withdrawn |
| Substation | Belmont-Harrison II |
| Point of interconnection | Belmont-Harrison 500 kV II |
| County | Doddridge |
| State | WV |
| Voltage | 500 kV |
| Capacity | 660 MW |
| Resource (as published) | Natural Gas |
| Resource category | Gas (normalised for filtering) |
| Target commercial operation | 2023-07-01 |
| Source dataset | serial |
Additional filed fields
| Project Type | Generation Interconnection |
|---|---|
| Mw Energy | 665 |
| Mw Capacity | 660 |
| Mfo | 665 |
| Withdrawn Date | 9/6/2019 |