Substation Scout

Braidwood-Davis Creek

PJM queue ID AE2-153 Terminal status

Queue IDAE2-153
Project nameBraidwood-Davis Creek
Status (as published)Withdrawn
SubstationBraidwood-Davis Creek
Point of interconnectionBraidwood-Davis Creek
CountyKankakee
StateIL
VoltageNot reported
Capacity35.2 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2021-03-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy200
Mw Capacity35.2
Mfo200
Withdrawn Date9/12/2023

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.