| Queue ID | AE2-138 |
|---|---|
| Project name | Avon-North Clark 345 kV |
| Status (as published) | Withdrawn |
| Substation | Avon-North Clark |
| Point of interconnection | Avon-North Clark 345 kV |
| County | Clark |
| State | KY |
| Voltage | 345 kV |
| Capacity | 20.8 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2022-06-01 |
| Source dataset | cycle |
Additional filed fields
| Developer | Geenex Solar, LLC |
|---|---|
| Transmission Owner | EKPC |
| Project Type | Generation Interconnection |
| Cycle | TC1 |
| Stage | PHASE 1 |
| Mw Energy | 260.0 |
| Mw Capacity | 20.8 |
| Mfo | 260.0 |
| Submitted Date | 3/8/2019 |
| Withdrawn Date | 1/22/2025 |
| Withdrawn Remarks | Customer Milestone Not Met |
| Last Updated | 1/24/2025 |