Substation Scout

Appalachian Cottontail Solar

PJM queue ID AE2-136 Terminal status

Queue IDAE2-136
Project nameAppalachian Cottontail Solar
Status (as published)Withdrawn
SubstationMuskingum River-W. Millersport
Point of interconnectionMuskingum River-W. Millersport 345 kV
CountyFairfield
StateOH
Voltage345 kV
Capacity83.2 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2028-12-31
Source datasetserial

Tracked changes

1 change observed between weekly snapshots of the PJM queue since PJM tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-09-07 Status change n/a Pending Termination → Withdrawn

Full change log →

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy114
Mw Capacity83.2
Mfo114
Withdrawn Date9/1/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.