Substation Scout

Levittown 13.2 kV

PJM queue ID AE2-097 Terminal status

Queue IDAE2-097
Project nameLevittown 13.2 kV
Status (as published)Withdrawn
SubstationLevittown
Point of interconnectionLevittown 13.2 kV
CountyBurlington
StateNJ
Voltage13.2 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2020-03-02
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy2
Mw Capacity0
Mfo2
Withdrawn Date8/14/2019

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.