Substation Scout

Hopewell 26 kV

PJM queue ID AE2-095 Terminal status

Queue IDAE2-095
Project nameHopewell 26 kV
Status (as published)Withdrawn
SubstationHopewell
Point of interconnectionHopewell 26 kV
CountyMercer
StateNJ
Voltage26 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Solar; Storage
Resource categoryHybrid (normalised for filtering)
Target commercial operation2020-03-02
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy2.145
Mw Capacity0
Mfo2.15
Withdrawn Date4/4/2019

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.