Substation Scout

Pierpoint-Freeport

PJM queue ID AE2-077 Terminal status

Queue IDAE2-077
Project namePierpoint-Freeport
Status (as published)Withdrawn
SubstationPierpoint-Freeport
Point of interconnectionPierpoint-Freeport
CountyWinnebago
StateIL
VoltageNot reported
Capacity26.6 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2021-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy70
Mw Capacity26.6
Mfo70
Withdrawn Date9/3/2019

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.