N. Meshoppen 34 kV

PJM queue ID AE2-067 Terminal status

Queue IDAE2-067
Project nameN. Meshoppen 34 kV
Status (as published)Withdrawn
SubstationN. Meshoppen
Point of interconnectionN. Meshoppen 34 kV
CountyWyoming
StatePA
Voltage34 kV
Capacity19.9 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2021-01-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy20
Mw Capacity19.9
Mfo20
Withdrawn Date9/4/2019

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.