Kerr Dam-Ridge Road 115 kV

PJM queue ID AE2-053 Terminal status

Queue IDAE2-053
Project nameKerr Dam-Ridge Road 115 kV
Status (as published)Withdrawn
SubstationKerr Dam-Ridge Road
Point of interconnectionKerr Dam-Ridge Road 115 kV
CountyMecklenburg
StateVA
Voltage115 kV
Capacity20 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2021-09-15
Source datasetcycle

Additional filed fields

DeveloperRWE Solar Development, LLC
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleTC1
StagePHASE 1
Mw Energy20.0
Mw Capacity20.0
Mfo110.0
Submitted Date2/1/2019
Withdrawn Date6/24/2024
Withdrawn RemarksCustomer Milestone Not Met
Last Updated6/24/2024