Substation Scout

Masury-Maysville 138 kV

PJM queue ID AE2-036 Terminal status

Queue IDAE2-036
Project nameMasury-Maysville 138 kV
Status (as published)Withdrawn
SubstationMasury-Maysville
Point of interconnectionMasury-Maysville 138 kV
CountyMercer
StatePA
Voltage138 kV
Capacity13.5 MW
Resource (as published)Solar; Storage
Resource categoryHybrid (normalised for filtering)
Target commercial operation2019-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy19.9
Mw Capacity13.5
Mfo19.9
Withdrawn Date8/12/2019

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.