Larrabee 230 kV I
PJM queue ID AE2-024 Terminal status
| Queue ID | AE2-024 |
|---|---|
| Project name | Larrabee 230 kV I |
| Status (as published) | Withdrawn |
| Substation | Larrabee I |
| Point of interconnection | Larrabee 230 kV I |
| County | Ocean |
| State | NJ |
| Voltage | 230 kV |
| Capacity | 155.2 MW |
| Resource (as published) | Offshore Wind |
| Resource category | Offshore Wind (normalised for filtering) |
| Target commercial operation | 2025-12-01 |
| Source dataset | serial |
Additional filed fields
| Project Type | Generation Interconnection |
|---|---|
| Mw Energy | 882 |
| Mw Capacity | 155.23 |
| Mfo | 882 |
| Withdrawn Date | 9/1/2023 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.