PJM queue ID AE2-012 Terminal status

Queue IDAE2-012
Project nameRed Oak-South River 230 kV
Status (as published)Withdrawn
SubstationRed Oak-South River
Point of interconnectionRed Oak-South River 230 kV
CountyMiddlesex
StateNJ
Voltage230 kV
Capacity540 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2023-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy570
Mw Capacity540
Mfo570
Withdrawn Date3/29/2019