Substation Scout

Nottingham-Peach Bottom Tap 230 kV line

PJM queue ID AE2-009 Terminal status

Queue IDAE2-009
Project nameNottingham-Peach Bottom Tap 230 kV line
Status (as published)Withdrawn
SubstationNottingham-Peach Bottom Tap line
Point of interconnectionNottingham-Peach Bottom Tap 230 kV line
CountyAdams
StatePA
Voltage230 kV
Capacity11 MW
Resource (as published)Not reported
Resource categoryNot reported (normalised for filtering)
Target commercial operation2020-06-01
Source datasetserial

Additional filed fields

Project TypeUpgrade Request
Mfo11
Withdrawn Date3/20/2020