Substation Scout

Reams 115 kV

PJM queue ID AE1-249 Terminal status

Queue IDAE1-249
Project nameReams 115 kV
Status (as published)Withdrawn
SubstationReams
Point of interconnectionReams 115 kV
CountyDinwiddie
StateVA
Voltage115 kV
Capacity40.1 MW
Resource (as published)Solar; Storage
Resource categoryHybrid (normalised for filtering)
Target commercial operation2021-12-31
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy70
Mw Capacity40.1
Mfo70
Withdrawn Date1/10/2020

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.